# Four 32-metre tanks are being built at the Minsk wastewater treatment plant

- URL: https://syn.by/en/society/minsk-wastewater-treatment-plant/
- Published: 2026-11-24T13:00:45+00:00
- Updated: 2026-11-24T20:07:34+00:00
- Section: Society
- Language: en
- RU edition: https://syn.by/ru/obshchestvo/minskaya-ochistnaya-stantsiya-rezervuar.md
- BE edition: https://syn.by/hramadztva/mienskaja-achyshchalnaja-stancyja-rezervuary.md

> Each tank is designed for 12000 cubic metres of sewage sludge. The plant plans to generate electricity from the biogas produced.

![](https://syn.by/wp-content/uploads/2026/11/illustration-9905-1024x585.webp)

Four monolithic tanks, 32 metres high, roughly the height of a ten-storey building, are being built at the same time as part of the reconstruction of the Minsk wastewater treatment plant. The builders call them digesters. The work is being carried out by SU-26 of Construction Trust No. 4. According to Minskstroi, monolithic tanks of this kind have not been built in Belarus before.

Each tank will have a volume of 12000 cubic metres. Inside, the sewage sludge will [ferment at a temperature of 55°C](https://t.me/mgjha/32476) without access to oxygen, and biogas will be released in the process.

The walls are cast from high-strength concrete in three-metre sections. Besides ordinary reinforcement, post-tensioned cables are laid in the concrete in several rows. Once the concrete has gained strength, the cables are tensioned with jacks and fixed with anchors, so that the walls can withstand pressure from inside.

Denis Drapei, director of Belkommunproekt, said in October that the plan is to generate electricity from the biogas produced. By his estimate, renewable sources will be able to cover about two thirds of the plant's energy needs.

There are plans to incinerate the sludge after dewatering in the future: ash will remain, and less waste will go to landfills. Minskstroi explains that the reconstruction is aimed at improving the quality of water treatment and reducing the volume of waste going to landfills.

The plant continues to treat wastewater while work goes on on its site. Some of the first-stage facilities have already been put into operation, and the updated line for preparing sludge for disposal is also working. More than 500 specialists are employed on the reconstruction.

By the end of 2026 the builders expect to hand over three aeration tanks for the biological treatment of wastewater, with a pumping station, and to complete the first stage.